DISTRIBUTION & OPERATION RACKS AND PANELS
These Racks and Panels are manufactured to stringent specifications to meet varied requirements of communications and are also manufactured to customer’s design and specifications.

Patching Shelf

Customer Premises Box
I. SHOWER TEST: To check integrity of the Racks and Panels against water penetration.
Spray -
 water
Flow Rate -
 40 Ltrs / min. / head
Number of heads -
 4
Head to Sample -
 400 ? 100 mm
Sample Position -
 Laying Down
Requirement -
 No Water ingress
II ENVIRONMENTAL CYCLE TEST: To determine working capability of the Rack and Panel for climatic conditions.

Lowest Temp. -
-15°C
Highest Temp. -

60°C
Dwell Time -
4 Hrs.
Transition Time -
2 Hrs.
Cycle Duration -
10:30 Hrs.
Number of Cycles -
10
III VIBRATION TEST: To check effect of Vibrations caused due to tempest, storm and other inclement weather conditions.


Waterproof PC/PT/Cable Inlet Arrangement
Planes -
3 (X, Y & Z axis)
Sweep -

(10-300) Hz ±2% at 1 octare±10% per min.

(a) Sine Sweep (10-28) ?? 1 Hz. 0.1” (2.5mm) double amplitude

Time -
2 Hrs. each axis

These Racks and Panels are tested for axial Tension of 70 Newtons applied longitudinally for 10 min. on the cables and for Pig Tails / Patch Cords the test is conducted at 25 Newtons for 10 min. (to simulate effect of accidental pull).